Copy a Zone, Event, or Replacement Day Schedule
Once you create zone, event, or replacement day schedules, you can copy them to reduce unnecessary repetition when you enter data. For example, copying is useful when a building has the same control requirements among floors.
Information
NOTE:
When you copy a zone schedule over to another zone, any overrides the zone may have are not copied.
- System Manager is in Engineering mode.
- You have the zone or event to which you want to copy an item displaying in the Apogee EQS tab.
- In System Browser, select Application View.
- From the Zone Editor or Event Editor in the Apogee EQS tab, open the Schedules expander.
- Do one of the following to copy a schedule to the active item:
- To copy a zone schedule: Navigate to Applications > Schedules > APOGEE Zones and drag-and-drop the zone over the Copy To field in the Schedules expander.
- To copy an event schedule: Navigate to Applications > Schedules > APOGEE Events and drag-and-drop the event over the Copy To field in the Schedules expander.
- To copy a replacement day schedule: Navigate to Applications > Schedules > APOGEE Replacement Days and drag-and-drop the replacement day over the Copy To field in the Schedules expander.
NOTE: Day shift schedules cannot be copied.
- Click Copy.
- The schedule displays in the Timeline for the current item.
- Click Saved .
- The copied schedule is saved.